State Route 431 Water Quality Improvement Project

Project Number
01.01.01.0039
Action Priority
Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
Implementers
Nevada Department of Transportation
Primary Contact
Chris Holman (cholman@dot.nv.gov)
Stage
Completed
Duration
? - 2012
Stormwater Management Program Reduce Stormwater Pollution From: Roads and Highways, Forest Roads, Public and Private Parcels
The project includes the design and implementation of water quality and erosion control features on SR431 between SR 28 and the Lake Tahoe Basin boundary. The project includes planning, design and construction for installation of source control, conveyance and treatment facilities for stormwater runoff. Aggressive storm water treatment and source control will be necessary in the lower portions of the project area as it dissected by Rosewood, Third, Incline and Wood Creeks as well as several other smaller tributaries and stream environment zones. Project Description required

Key Accomplishments

  • Miles of Roads Decommissioned or Retrofitted: 6.6 miles

Threshold Categories

  • Water Quality

No Key Photo provided for this Project

Location

Expenditures

Expenditures by Funding Source to Date: $8,565,408
(Estimated Cost: $8,565,408)
Southern Nevada Publi... (USFS - LTBMU): $1,599,280

U.S. Federal Highway Administ... (FHWA): $1,600,000

Nevada Department of Transpor... (NDOT): $46,000

Nevada State Gas Tax (NDOT): $2,800,000

Tahoe Bonds Act (NDSL): $2,520,128

Photos

No additional photos provided